Noticias y novedades

Las novedades más relevantes sobre Hidroituango S.A. y el avance del proyecto. Aquí reunimos publicaciones, actualizaciones, hitos constructivos, acciones sociales y ambientales, y toda la información que refleja el desarrollo diario de la empresa.

Hidroituango engineers verify progress on the La Angelina Bridge, a key project for mobility in Liborina

Engineers from HIDROITUANGO S.A. carried out a technical verification visit to the works of the La Angelina Bridge, a strategic infrastructure to improve the mobility and connectivity of the communities of La Angelina and Mogotes with the urban area of the municipality of Liborina. The visit took place on November 26, 2025 and made it possible to evaluate the current state of the work, compliance with the schedule and the technical conditions associated with the future filling of the reservoir.

December 16, 2025

Engineers from HIDROITUANGO S.A. carried out a technical verification visit to the works of La Angelina Bridge, a strategic infrastructure to improve the mobility and connectivity of communities of La Angelina y Mogotes with the urban area of the municipality of Liborina. The visit took place on November 26, 2025 and made it possible to evaluate the current state of the work, compliance with the schedule and the technical conditions associated with the future filling of the reservoir.

The bridge, which will have a Length of 180 meters And a Width of 4 meters, is erected on two main supports, each one based on eight batteries of 1.5 meters in diameter. The structure has a cost of 44.9 billion pesos It is estimated that it will be completed in August 2026.

During the verification, engineers noted progress in the Emptying the foundation batteries, as well as in the preparation of Of the upper data of 8.5 m x 8.5 m x 2.5 m, located at an elevation of 417 meters above sea level. Above these will rise the columns of 33 meters high, necessary to reach the level of the bridge in the 450 meters above sea level.

A revised critical point was compliance with the Minimum altitude of 425 meters above sea level in the columns, required to ensure that the work does not interfere with filling the reservoir up to 420 meters above sea level. According to the technical evaluation, this objective can be achieved In mid-January 2026, without affecting the filling schedule, scheduled for April 2026.

The La Angelina Bridge represents an investment with a high social impact and a substantial improvement in the quality of life of thousands of inhabitants of the region, reaffirming Hidroituango's commitment to territorial development and community infrastructure.

Te puede interesar

March 12, 2026

Colombia está cerca de un apagón técnico y financiero, revela análisis del sector eléctrico realizado por HIDROITUANGO S.A.

Un análisis de Hidroituango S.A. advierte que el sistema eléctrico colombiano se encuentra cerca de un apagón técnico y financiero debido a la reducción de la capacidad efectiva de generación, que en 2025 cayó en unos 341 MW pese a la entrada de nuevos proyectos. El estudio señala que factores regulatorios hicieron que 47 plantas (581 MW) regresaran a estado de pruebas, disminuyendo la energía firme disponible frente a una demanda creciente. Aunque la central Central Hidroeléctrica Ituango ha aportado cerca del 10,9 % de la energía del país y ha ayudado a mitigar el riesgo, el informe advierte que se requieren nuevas inversiones y proyectos de generación y transmisión para garantizar la confiabilidad del sistema eléctrico en el mediano plazo.
March 12, 2026

Colombia está cerca de un apagón técnico y financiero, revela análisis del sector eléctrico realizado por HIDROITUANGO S.A.

Informe Técnico #4
March 5, 2026

La inestabilidad jurídica de Colombia espanta la inversión en proyectos de energía: Alejandro Arbeláez, Gerente de HIDROITUANGO S.A.

El gerente de Hidroituango S.A., Alejandro Arbeláez, advirtió que la inestabilidad jurídica y las dificultades normativas en Colombia están desincentivando la inversión en proyectos de generación de energía y poniendo en riesgo el desarrollo del sector.